Server Power Consumption Calculator — Watts, Units & ₹ Bill per Month
Server kitni bijli khata hai? Model chuniye ya CPU, RAM, disk, GPU daaliye — watts, mahine ke units (kWh) aur ₹ bill turant. Purane aur naye server ki tulna karke saal ki bachat bhi dekhiye.
Your server / Aapka server
Edit CPUs, RAM, disks, GPU / Config badlein
Usage & tariff / Chalne ka time aur rate
Office file/Tally server: 10–30% · VMs/database: 30–60% · rendering/AI: 70–100%
State rates sirf rough commercial average hain — sahi hisaab ke liye apne bijli bill ka ₹/unit (fixed charges + duty sahit) daalein.
Kahan kitni bijli / Where the watts go (at 40% load)
- Motherboard, fans, BMC85 W
- CPU122 W
- RAM22 W
- Disks20 W
- PSU loss (90% efficient)28 W
Bijli bill kam karna hai? Sahi size ka server lijiye.
Purane R710/G7 jaise servers se Gen10/R740 class par shift karke kam watts mein zyada kaam. Refurbished Dell/HPE ya ProStation build, tested, GST invoice, 1-year warranty.
How to use / Kaise use karein
- Server model/class chuniye (jaise R730 / DL380 Gen9) ya 'Custom' mein CPU, RAM, disk aur GPU daaliye.
- Average load set kariye — office server aam taur par 10–30% par chalta hai.
- Roz kitne ghante chalta hai aur apna state chuniye; behtar hai apne bill ka ₹/unit daalein.
- AC room mein hai to AC option chuniye.
- Purana vs naya compare karna ho to tick kariye — saal ki bachat aur payback dikhega.
Formula & assumptions
- Component power:
idle + (max − idle) × load%for platform (board, fans, BMC), CPUs (TDP), RAM sticks, disks and GPUs. - Wall watts =
DC watts ÷ PSU efficiency(80 PLUS 230 V redundant at ~20% load: Bronze 81%, Gold 88%, Platinum 90%, Titanium 94%). - Units per month =
watts × hours/day × 30 ÷ 1000· per year =× 365. - ₹ = units × ₹/unit · with AC: × 1.3 or × 1.6.
- Heat (BTU/h) = watts × 3.412.
Typical figures used: CPU idle ≈ 20% (new), 30% (2014–17), 45% (older) of TDP; DDR4 stick 2–4 W; 3.5" HDD 5–9 W; SSD 1–3.5 W; NVMe 5–12 W. State ₹/unit values are rough commercial averages — use your own bill.
FAQ
Q.Server kitni bijli khata hai?
Ek normal office tower server 60–150 watt aur ek dual-CPU 2U rack server 150–400 watt leta hai, load ke hisaab se. 200 watt ka server 24 ghante chale to 200 × 24 ÷ 1000 = 4.8 unit roz, yaani ~144 unit mahina. ₹10/unit par ~₹1,440 mahina.
Q.How do I calculate server electricity units per month?
Units (kWh) per month = average watts × hours per day × 30 ÷ 1000. One unit on an Indian electricity bill is one kWh. Multiply the units by your ₹/unit rate (including fixed charges and duty) to get the monthly cost.
Q.Is the PSU wattage (e.g. 750 W) what the server actually uses?
No. The power supply rating is the maximum it can deliver. A server with two 750 W PSUs may draw only 150–300 W in normal use. Use the calculator or the iDRAC/iLO power meter to see the real draw.
Q.Purana server (R710 / G7) chalana mehenga padta hai kya?
Haan, aksar. Purane Xeon 5600 generation servers idle par hi ~200 watt+ le lete hain. Same kaam Gen10/R740 class server kam watts mein karta hai, aur 24×7 chalne par saal mein kuch hazaar rupaye ki bijli bachti hai. Calculator mein 'Compare old vs new' se apna figure dekhiye.
Q.What is PSU efficiency and why does it matter?
A power supply wastes some energy as heat. An 80 PLUS Platinum PSU is about 90% efficient at light load, so a server needing 200 W inside draws about 222 W from the wall. Older or unrated PSUs waste more.
Q.Should I add air-conditioning cost?
If the server sits in an AC room, the AC must remove the server's heat too. Small server rooms often spend 30–60% extra on cooling. Pick the AC option in the calculator to include it. The BTU/h figure helps size the AC.
Q.How accurate is this calculator?
It is a planning estimate, typically within ±20% for standard servers. Real draw depends on BIOS power profile, fan speed, room temperature and workload. For an exact number measure with a plug-in power meter or the server's iDRAC/iLO power graph for a week.
Related guides & servers
More free calculators
- RAID Calculator — usable TB, fault tolerance, speed
- CCTV Storage Calculator — TB needed, recording days, NVR/server
- Tally / Busy Server Sizing Calculator — RAM, CPU, SSD for Tally/Busy users
Updated 2026-11-17. Results are planning estimates — share them with us on WhatsApp and we'll check them against a real build.